| ER-VI-9999(140) |
Traffic Signs STX |
St. Croix |
FHWA-Emergency Repairs |
Permanent Traffic Signs STX |
Procurement Process |
Pending |
13,20,457.00 |
Procurement |
| |
North Side Road |
St. Thomas |
CDBG-DR |
Rehabilitation of Roadway |
Procurement still in Negotiations for an A& E firm. |
|
$5,00,00,000.00 |
Procurement |
| |
Donoe Road |
St. Thomas |
CDBG-DR |
Rehabilitation of Roadway |
Contract process of awarding the design to Kimley Horn. Anticpate starting early 2021 for Design. |
|
$1,62,53,869.97 |
Contract Execution |
| |
Queen Mary Highway |
St. Croix |
CDBG-DR |
Rehabilitation of Roadway |
Application still at HFA for consideration pending approval for design. HFA to reach out to DPW to work on cost assessment analysis |
|
$9,67,49,226.01 |
Procurement |
| |
Hospital Gade, Mafolie Road |
St. Thomas |
CDBG-DR |
Rehabilitation of Roadway |
Application Development |
|
$1,06,03,715.17 |
Project Development |
| |
Bolongo Road |
St. Thomas |
CDBG-DR |
Rehabilitation of Roadway |
Application Development |
|
$2,56,96,594.43 |
Project Development |
| |
Centerline Road |
St. Croix |
CDBG-DR |
Rehabilitation of Roadway |
Application still at HFA for consideration pending approval for design. HFA to reach out to DPW to work on cost assessment analysis |
|
$2,25,23,219.81 |
Procurement |
| |
Veterans Drive |
St. Thomas |
CDBG-DR |
Rehabilitation of Roadway |
Phase II in Design Process |
|
$10,00,00,000.00 |
Design |
| 0066012 |
Melvin Evans Highway |
St. Croix |
GARVEE BONDS |
Rehabilitation of Roadway |
In Construction. Project broken up into six segments. Three segments are complete. Two segments are in active construction (17 is 75% and 14 is 50%). One segment (13) in final design phase. |
VI-66(12) - VI Paving, VI-66(15) - VI Paving, VI-66(16) - VI Paving, VI-66(14) - VIAPCO, VI-66(17) - VI Paving |
1,50,00,000.00 |
Active Construction |
| 9999136 |
Frederiksted Roads
(Routes 7023,7025,7027,7029,702) |
St. Croix |
GARVEE BONDS |
Rehabilitation of Roadway |
VI-9999(13) Consultant design plans FHWA review. Will go to bid 2020. |
TBD |
30,00,000.00 |
Design |
| 9999135 |
Christiansted Roads
(75E,75W,754) |
St. Croix |
GARVEE BONDS |
Rehabilitation of Roadway |
In design (EFL) |
TBD |
30,00,000.00 |
Design |
| 63001 |
Hams Bluff Road |
St. Croix |
GARVEE BONDS |
Rehabilitation of Roadway |
Developing RFP for design services |
TBD |
70,00,000.00 |
Project Development |
| 76001 |
Mahogany Road |
St. Croix |
GARVEE BONDS |
Rehabilitation of Roadway |
Consultant design in progress (95%). Bid late 2020. |
TBD |
80,00,000.00 |
Design |
| 74001 |
Rattan Road |
St. Croix |
GARVEE BONDS |
Rehabilitation of Roadway |
VI-74(1) Design Plans to be developed in-house. not yet started. |
TBD |
30,00,000.00 |
Project Development |
| 85002 |
Spring Gut Road |
St. Croix |
GARVEE BONDS |
Rehabilitation of Roadway |
Consultant design in progress. ROW acquisitions have commenced. |
TBD |
77,30,750.00 |
Active Construction |
| 81002 |
Sion Valley |
St. Croix |
GARVEE BONDS |
Rehabilitation of Roadway |
Project 80% complete. Construction ongoing. |
VI Paving |
66,85,425.00 |
Active Construction |
| A034002 |
Veterans Drive Phase I |
St. Thomas |
GARVEE BONDS |
Rehabilitation of Roadway |
Project 80% Complete. Construction in progress. |
American Bridge |
4,29,64,906.18 |
Active Construction |
| VI ST ER STJ(002), STT(004) |
Route 333 - Site 1 |
St. Thomas |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 13 sites on St. Thomas damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
|
Contruction: $19,766,422.33 Prelim. Engineering: $105,932.79 |
Procurement |
| VI ST ER STJ(002), STT(004) |
Route 334 - Site 3 (Crown Mountain Road) |
St. Thomas |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 13 sites on St. Thomas damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
|
Contruction: $19,766,422.33 Prelim. Engineering: $105,932.80 |
Procurement |
| VI ST ER STJ(002), STT(004) |
Route 335 - Site 1 |
St. Thomas |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 13 sites on St. Thomas damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
|
Contruction: $19,766,422.33 Prelim. Engineering: $105,932.81 |
Procurement |
| VI ST ER STJ(002), STT(004) |
Route 33 - Shibui |
St. Thomas |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 13 sites on St. Thomas damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
|
Contruction: $19,766,422.33 Prelim. Engineering: $105,932.82 |
Procurement |
| VI ST ER STJ(002), STT(004) |
Route 30 - MP 0.9 (Fortuna Road) |
St. Thomas |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 13 sites on St. Thomas damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
|
Contruction: $19,766,422.33 Prelim. Engineering: $105,932.83 |
Procurement |
| VI ST ER STJ(002), STT(004) |
Route 30 - Black Point Hill to Daisy RB |
St. Thomas |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 13 sites on St. Thomas damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
|
Contruction: $19,766,422.33 Prelim. Engineering: $105,932.84 |
Procurement |
| VI ST ER STJ(002), STT(004) |
Route 33 & 40 |
St. Thomas |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 13 sites on St. Thomas damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
|
Contruction: $19,766,422.33 Prelim. Engineering: $105,932.85 |
Procurement |
| VI ST ER STJ(002), STT(004) |
Route 33 - Site 3 |
St. Thomas |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 13 sites on St. Thomas damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
|
Contruction: $19,766,422.33 Prelim. Engineering: $105,932.86 |
Procurement |
| VI ST ER STJ(002), STT(004) |
Route 37 - Site 6 Hull Bay Road |
St. Thomas |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 13 sites on St. Thomas damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
|
Contruction: $19,766,422.33 Prelim. Engineering: $105,932.87 |
Procurement |
| VI ST ER STJ(002), STT(004) |
Route 38 Weymouth Rhymer Road |
St. Thomas |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 13 sites on St. Thomas damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
|
Contruction: $19,766,422.33 Prelim. Engineering: $105,932.88 |
Procurement |
| VI ST ER STJ(002), STT(004) |
Route 42 - MP 1.3 (Mandal Road) |
St. Thomas |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 13 sites on St. Thomas damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
|
Contruction: $19,766,422.33 Prelim. Engineering: $105,932.89 |
Procurement |
| VI ST ER STJ(002), STT(004) |
Route 379 - Site 7 (Area 1 & 2) (Alexander Gade Road ) |
St. Thomas |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 13 sites on St. Thomas damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
|
Contruction: $19,766,422.33 Prelim. Engineering: $105,932.90 |
Procurement |
| VI ST ER STJ(002), STT(004) |
Route 3017 (Vested Gade Road) |
St. Thomas |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 13 sites on St. Thomas damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
|
Contruction: $19,766,422.33 Prelim. Engineering: $105,932.91 |
Procurement |
| VI ST ER STX(003) |
Route 64- East Airport Road Bridge |
St. Croix |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 16 sites on St. Croix damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
TBD |
Contruction: $10,660,446.43 Prelim. Engineering: $115,507.48 |
Procurement |
| VI ST ER STX(003) |
Route 72 - MP 1.4 Midland Road Bridge |
St. Croix |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 16 sites on St. Croix damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
TBD |
Contruction: $10,660,446.43 Prelim. Engineering: $115,507.49 |
Procurement |
| VI ST ER STX(003) |
Route 7532 - MP 0.02 (Gallows Bay Road) |
St. Croix |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 16 sites on St. Croix damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
TBD |
Contruction: $10,660,446.43 Prelim. Engineering: $115,507.50 |
Procurement |
| VI ST ER STX(003) |
Route 82 - MP 0.5 (East End Road) |
St. Croix |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 16 sites on St. Croix damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
TBD |
Contruction: $10,660,446.43 Prelim. Engineering: $115,507.51 |
Procurement |
| VI ST ER STX(003) |
Route 82 - MP 2.5 (East End Road) |
St. Croix |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 16 sites on St. Croix damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
TBD |
Contruction: $10,660,446.43 Prelim. Engineering: $115,507.52 |
Procurement |
| VI ST ER STX(003) |
Route 82 - MP 3.5 (East End Road) |
St. Croix |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 16 sites on St. Croix damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
TBD |
Contruction: $10,660,446.43 Prelim. Engineering: $115,507.53 |
Procurement |
| VI ST ER STX(003) |
Route 753 (Mt Welcome Road) |
St. Croix |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 16 sites on St. Croix damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
TBD |
Contruction: $10,660,446.43 Prelim. Engineering: $115,507.54 |
Procurement |
| VI ST ER STX(003) |
Route 763 - MP 0.0 |
St. Croix |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 16 sites on St. Croix damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
TBD |
Contruction: $10,660,446.43 Prelim. Engineering: $115,507.55 |
Procurement |
| VI ST ER STX(003) |
Route 765 - MP 0.0 (Annaly Road) |
St. Croix |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 16 sites on St. Croix damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
TBD |
Contruction: $10,660,446.43 Prelim. Engineering: $115,507.56 |
Procurement |
| VI ST ER STX(003) |
Rotue 63 - MP 0.9 Concordia Road |
St. Croix |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 16 sites on St. Croix damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
TBD |
Contruction: $10,660,446.43 Prelim. Engineering: $115,507.57 |
Procurement |
| VI ST ER STX(003) |
Route 66 - MP 2.9 Melvin Evans Highway |
St. Croix |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 16 sites on St. Croix damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
TBD |
Contruction: $10,660,446.43 Prelim. Engineering: $115,507.58 |
Procurement |
| VI ST ER STX(003) |
Route 78 - West Scenic Road in Sweet Bottom |
St. Croix |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 16 sites on St. Croix damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
TBD |
Contruction: $10,660,446.43 Prelim. Engineering: $115,507.59 |
Procurement |
| VI ST ER STX(003) |
Route 80 - MP 0.8 North Shore Road |
St. Croix |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 16 sites on St. Croix damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
TBD |
Contruction: $10,660,446.43 Prelim. Engineering: $115,507.60 |
Procurement |
| VI ST ER STX(003) |
Route 80 North Shore Road- East Culverts |
St. Croix |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 16 sites on St. Croix damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
TBD |
Contruction: $10,660,446.43 Prelim. Engineering: $115,507.61 |
Procurement |
| VI ST ER STX(003) |
Route 80 North Shore Road - West Single Culvert |
St. Croix |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 16 sites on St. Croix damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
TBD |
Contruction: $10,660,446.43 Prelim. Engineering: $115,507.62 |
Procurement |
| VI ST ER STX(003) |
Route 732 Windor Road |
St. Croix |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 16 sites on St. Croix damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
TBD |
Contruction: $10,660,446.43 Prelim. Engineering: $115,507.63 |
Procurement |
| VI ST ER STJ(002), STT(004) |
Route 104 - Site 1 (Southside Road) |
St. John |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 5 sites on St. John damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
TBD |
TBD |
Procurement |
| VI ST ER STJ(002), STT(004) |
Route 104 - Site 2(Southside Road) |
St. John |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 5 sites on St. John damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
TBD |
TBD |
Procurement |
| VI ST ER STJ(002), STT(004) |
Route 107 |
St. John |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 5 sites on St. John damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
TBD |
TBD |
Procurement |
| VI ST ER STJ(002), STT(004) |
Route 108 Bordeaux Mountain Road |
St. John |
FHWA-Emergency Repairs |
Rehabilitation of roadways, culverts, embankments, and other roadway features of 5 sites on St. John damaged by Hurricanes Irma and Maria. |
Design-Build (DB) procurement in progress |
TBD |
TBD |
Procurement |