PROJECT TITLE: Adrian Road Route 10 Pavement Rehabilitation
ISLAND: St. John
DATES: September 28 - March 2021
HOURS OF WORK: 7:30 am - 4:30 pm
SUMMARY: Construction will begin on the Adrian Road Project on September 28 with the implementation of temporary traffic controls. The project limits include the Intersection of Route 10 and Route 206 heading West along Centerline Road. The contractor is Grace Civil LLC.
SCOPE OF WORK: Roadway Excavation, Reinforced Concrete Pavement, Guardrail Removal and Replacement, Pavement Restoration
ESTIMATED PROJECT COST: $715,260.00
The Department of Public Works appreciates the community's patience as they work to improve road conditions throughout the territory. Follow DPW on Facebook @usvidpw and @vitranusvi. You can also log on to www.dpw.vi.gov and www.vitranvi.com to stay abreast of all things V.I. Public Works.
DPW…On the move!